  • Car Park Surfacing (HIGH1)

    Policy

    Before the development is brought into use, that part of the site to be used by vehicles shall be surfaced, drained and where necessary marked out in a manner to be submitted and approved in writing by the Local Planning Authority.

    Reference
    U0111829
  • Car Park Retention (HIGH3)

    Policy

    Before the development hereby permitted is brought into use, the parking as shown on the approved plans shall be provided. The parking area shall not be used otherwise than for the parking of private motor vehicles belonging to the employees of and visitors to the development hereby approved.

    Reference
    U0111830
  • Approved Plans

    Policy

    The development hereby permitted must be carried out and completed entirely in accordance with the terms of this permission and the details shown on the approved plans listed below: - Site Plan (received 16 March 2023)

    Reference
    U0111831
  • Ecological Enhancement Plan

    Policy

    Within 6 months of the date of this permission, an ecological enhancement plan shall be implemented. This ecological enhancement plan shall be based on the measures as set out in Section 2 of the report (Ref: Ecological Enhancement Plan, Estrada Ecology SQ1099, 26th June 2023) and implemented in accordance with the recommendations in Section 3 and particularly Table 1. Photographic evidence of implementation must be submitted to and approved in writing by the Local Planning Authority.

    Reference
    U0111832
  • Implementation

    Policy

    The development to which this permission relates must be begun not later than the expiration of three years beginning with the date of this permission.

    Reference
    U0111833
  • Approved Plans

    Policy

    The development hereby permitted must be carried out and completed entirely in accordance with the terms of this permission and the details shown on the approved plans listed below: - Location Plan (001) (Rev P2) (received 27 April 2023) - Proposed Site Plan (100) (Rev P4) (received 27 July 2023) - Proposed Elevations (310) (Rev P2) (received 27 April 2023) - Proposed Ground & First Floor Plans (310) (Rev P1)

    Reference
    U0111834
  • Drainage DA01

    Policy

    The development hereby granted shall not be begun until details of the foul, surface water and land drainage systems and all related works necessary to drain the site have been submitted to and approved by the Local Planning Authority. These works shall be carried out concurrently with the development and the drainage system shall be operating prior to the occupation of the development.

    Reference
    U0111835
  • Yorkshire Water - Liquid Storage Tanks

    Policy

    Any liquid storage tanks should be located within a bund with a capacity of not less than 110% of the largest tank or largest combined volume of connected tanks.

    Reference
    U0111836
  • Yorkshire Water - CEMP

    Policy

    Prior to the commencement of development, a Construction Environmental Management Plan (CEMP) shall be submitted to and approved in writing by the Local Planning Authority to understand the impact of planning permission on the sewerage system. The development shall thereafter be carried out in accordance with the CEMP.

    Reference
    U0111837
  • Yorkshire Water - Piped Discharge

    Policy

    There shall be no piped discharge of surface water from the development prior to the completion of surface water drainage works, details of which will have been submitted to and approved by the Local Planning Authority prior to the commencement of above ground works. If discharge to a public sewer is proposed, the information shall include, but not be exclusive to:- a) evidence to demonstrate that surface water disposal via infiltration or watercourse are not reasonably practical; b) evidence of existing positive drainage to public sewer and the current points of connection; and c) the means of restricting the discharge to public sewer to the existing rate less a minimum 30% reduction, based on the existing peak discharge rate during a 1 in 1 year storm event, to allow for climate change.

    Reference
    U0111838