Planning condition

CON1 minus part A

Field Value Fact links
Reference U0110561 Facts
Prefix planning-condition Facts
Name CON1 minus part A Facts
Dataset Planning condition no fact link
Organisation Doncaster Metropolitan Borough Council no fact link
Start date no fact link
End date no fact link
Entry date 2025-02-25 Facts
Typology policy no fact link
Notes Unique Condition Facts
Reason To secure the satisfactory development of the site in terms of human health and the wider environment and pursuant to guidance set out in the National Planning Policy Framework. This is required prior to commencement to ensure that the necessary mitigation measures can be put in place should any contamination be found. Facts
Description No development approved by this permission shall be commenced prior to a contaminated land assessment and associated remedial strategy, together with a timetable of works, being accepted and approved by the Local Planning Authority (LPA), unless otherwise approved in writing with the LPA. b) The Phase 2 site investigation and risk assessment, if appropriate, must be approved by the LPA prior to investigations commencing on site. The Phase 2 investigation shall include relevant soil, soil gas, surface and groundwater sampling and shall be carried out by a suitably qualified and accredited consultant/contractor in accordance with a quality assured sampling and analysis methodology and current best practice. All the investigative works and sampling on site, together with the results of analysis, and risk assessment to any receptors shall be submitted to the LPA for approval. c) If as a consequence of the Phase 2 Site investigation a Phase 3 remediation report is required, then this shall be approved by the LPA prior to any remediation commencing on site. The works shall be of such a nature as to render harmless the identified contamination given the proposed end-use of the site and surrounding environment including any controlled waters, the site must not qualify as contaminated land under Part 2A of the Environment Protection Act 1990 in relation to the intended use of the land after remediation. d) The approved Phase 3 remediation works shall be carried out in full on site under a quality assurance scheme to demonstrate compliance with the proposed methodology and best practice guidance. The LPA must be given two weeks written notification of commencement of the remediation scheme works. If during the works, contamination is encountered which has not previously been identified, then all associated works shall cease until the additional contamination is fully assessed and an appropriate remediation scheme approved by the LPA. e) Upon completion of the Phase 3 works, a Phase 4 verification report shall be submitted to and approved by the LPA. The verification report shall include details of the remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology. Details of any post-remedial sampling and analysis to show the site has reached the required clean-up criteria shall be included in the verification report together with the necessary documentation detailing what waste materials have been removed from the site. The site shall not be brought into use until such time as all verification data has been approved by the LPA. Facts

Contents

{
    "reference": "U0110561",
    "prefix": "planning-condition",
    "name": "CON1 minus part A",
    "dataset": "planning-condition",
    "organisation-entity": "109",
    "start-date": "",
    "end-date": "",
    "entry-date": "2025-02-25",
    "typology": "policy",
    "geometry": "",
    "point": "",
    "entity": 73000697,
    "notes": "Unique Condition",
    "reason": "To secure the satisfactory development of the site in terms of human health and the wider environment and pursuant to guidance set out in the National Planning Policy Framework. This is required prior to commencement to ensure that the necessary mitigation measures can be put in place should any contamination be found.",
    "description": "No development approved by this permission shall be commenced prior to a contaminated land assessment and associated remedial strategy, together with a timetable of works, being accepted and approved by the Local Planning Authority (LPA), unless otherwise approved in writing with the LPA. b) The Phase 2 site investigation and risk assessment, if appropriate, must be approved by the LPA prior to investigations commencing on site. The Phase 2 investigation shall include relevant soil, soil gas, surface and groundwater sampling and shall be carried out by a suitably qualified and accredited consultant/contractor in accordance with a quality assured sampling and analysis methodology and current best practice. All the investigative works and sampling on site, together with the results of analysis, and risk assessment to any receptors shall be submitted to the LPA for approval. c) If as a consequence of the Phase 2 Site investigation a Phase 3 remediation report is required, then this shall be approved by the LPA prior to any remediation commencing on site. The works shall be of such a nature as to render harmless the identified contamination given the proposed end-use of the site and surrounding environment including any controlled waters, the site must not qualify as contaminated land under Part 2A of the Environment Protection Act 1990 in relation to the intended use of the land after remediation. d) The approved Phase 3 remediation works shall be carried out in full on site under a quality assurance scheme to demonstrate compliance with the proposed methodology and best practice guidance. The LPA must be given two weeks written notification of commencement of the remediation scheme works. If during the works, contamination is encountered which has not previously been identified, then all associated works shall cease until the additional contamination is fully assessed and an appropriate remediation scheme approved by the LPA. e) Upon completion of the Phase 3 works, a Phase 4 verification report shall be submitted to and approved by the LPA. The verification report shall include details of the remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology. Details of any post-remedial sampling and analysis to show the site has reached the required clean-up criteria shall be included in the verification report together with the necessary documentation detailing what waste materials have been removed from the site. The site shall not be brought into use until such time as all verification data has been approved by the LPA."
}

© Crown copyright and database right 2025

Licensed under the Open Government Licence v.3.0.


Help improve this data

Give feedback on this dataset, or email your questions and corrections to digitalland@communities.gov.uk.